1
[Max] General Discussion / Corona DR + deadline problem
« on: 2021-12-20, 16:44:03 »
Hello. We are trying to switch to deadline in our studio. Our pipeline is generally 3ds max + Corona.
I have a problem with DBR rendering. When we submit job with DBR rendering turned on for let's say 4 workers everything seems ok.
But when not all 4 workers are available the job won't start at all. Worker assigned to task 0 from this job ( meant to be master) is showing in log that:
" Corona DR: Waiting for all job tasks to be dequeued before starting distributed render"
It is very bad solution for us- I would like to start this job even only with one worker available.
I read in documentation that Vray DBR offer such option - "Dynamic start". Is it possible to get the same in Corona DBR?
Anybody came to a solution?
I have a problem with DBR rendering. When we submit job with DBR rendering turned on for let's say 4 workers everything seems ok.
But when not all 4 workers are available the job won't start at all. Worker assigned to task 0 from this job ( meant to be master) is showing in log that:
" Corona DR: Waiting for all job tasks to be dequeued before starting distributed render"
It is very bad solution for us- I would like to start this job even only with one worker available.
I read in documentation that Vray DBR offer such option - "Dynamic start". Is it possible to get the same in Corona DBR?
Anybody came to a solution?